Typical concrete masonry unit bond beam reinforcing requirements are arranged with a center line wall layout. The reinforcing bar lap splice requires a development length of Lcmu plus an end development length Le. The 180-degree hook detail specifies a bend diameter D with a tail length of four times the bar diameter, or a two-and-one-half-inch minimum. Vertical reinforcing bars are placed per the CMU non-load bearing wall reinforcing schedule.
4db, OR 2 1/2" MIN db 180 DEGREE HOOK 6" db D 4db, OR 2 1/2" MIN 49" 7" Lcmu Le TYPE A TYPE B TYPE C CL WALL VERT PER "CMU NON-LOAD BEARING WALL REINF SCHED" BOND BEAM 13 TYPICAL CMU BOND BEAM REINFORCING