A post-tensioned concrete slab thickness transition features post-tensioned beams on either side of a stepped floor profile. The assembly incorporates post-tensioned tendons and slab reinforcing per plan, supplemented by four number four top bars and a Z-bar at the thickness break. An exterior topping slab is installed over weatherproofing per the architectural drawings, with the exterior slab sloped as required and a one-inch chamfer formed at the lower beam edge.
#4x3'-0" @ 12" O.C. (4) #4 IN TOP OF SLAB SLAB REINFORCING PER PLAN PT TENDON PER PLAN PT CONCRETE SLAB PER PLAN EDGE OF SLAB TRANSITION SEE PLAN TOPPING SLAB PER PLAN WEATHER PROOFING PER ARCH SLOPE EXTERIOR SLAB AS REQ'D LAP SPLICE PT BM PER PLAN Z-BAR PER 20/S5.30 1" CHAMFER