This concrete slab construction joint features continuous top reinforcing running through the joint where it occurs. A continuous key is formed at the middle one-third of the slab depth. Continuous bottom reinforcing also runs through the joint. Number 5 dowels measuring five feet zero inches in length are placed at twelve inches on center at the slab mid-depth.
3/4" "t" CONTINUOUS TOP REINFORCING THROUGH JOINT WHERE OCCURS. CONTINUOUS KEY REQUIRED AT MIDDLE 1/3 OF SLAB DEPTH CONTINUOUS BOT. REINF. THROUGH JOINT #5 x 5'-0" @ 12" O.C. PLACE DOWELS @ SLAB MID-DEPTH