Trench excavation runs parallel to building foundations requiring a minimum ten foot width and a one foot six inch clearance from the footing edge. The bottom of the trench excavation shall not extend below the sloped plane defined by a two to one ratio. Backfill must be placed per the soils report specifications. The contractor remains responsible for shoring, sheathing, and maintaining excavation sides to prevent cave-ins until backfill is completed.
2 2 1 1 NOTE: THE CONTRACTOR SHALL BE RESPONSIBLE FOR SHORING, SHEATHING OR OTHERWISE MAINTAINING THE SIDES OF THE EXCAVATION FROM CAVE-INS UNTIL ALL BACKFILL IS COMPLETED PER SPECIFICATIONS. BOTTOM OF TRENCH EXCAVATION SHALL NOT EXTEND BELOW THIS LINE BACKFILL PER SOILS REPORT 10'-0" MIN EXCAVATION TRENCH WIDTH FOOTING 1'-6" MIN