A structural slab per plan bears on structural beams with a concrete curb at the slab transition. A topping slab sits above the structural slab, incorporating high-density foam when the overall slab thickness exceeds ten inches including the deck. A concrete curb rises at grid line J.2 below the curtain wall assembly. Supporting steel beams span between grid lines K and J per plan.
Level 1 0" J J.2 K BEAM AT SLAB TRANSITION PER PLAN BEAM PER PLAN, TYP. CURTRAIN WALL, S.A.D. CONC. CURB TOPPING SLAB PER PLAN PROVIDE 25 # HIGH DENSITY FOAM IF SLAB THICKNESS IS MORE THEN 10" THICK (INCLUDING THE DECK ) STR. SLAB PER PLAN NOTE: SEE 4/S5.24 FOR INFO NOT NOTED. 3