A steel beam connects to a braced frame column using a welded-bolted moment connection assembly. Top and bottom continuity plates match the beam thickness and are welded across the column web. A shear tab sized to match the beam web thickness minus 1/16 inch is welded to the column face and receives three 7/8-inch diameter erection bolts. Weld access holes are provided at both the top and bottom beam flanges to facilitate the moment connection welds.
BRACED FRAME COLUMN, SEE PLAN AND SCHEDULE STEEL BEAM, SEE PLAN AND ELEVATIONS WELD ACCESS HOLE, TOP AND BOTTOM, MINUS 1/16" SHEAR TAB THICKNESS 7/8"DIA ERECTION BOLTS (3/8" MIN) PROVIDE (3) THICKNESS OF BEAM WEB. SHEAR TAB TO MATCH 3 OR CRITICAL WELD DEMAND CRITICAL WELD CONTINUITY PLATE TOP AND BOTTOM TO MATCH BEAM THICKNESS E