A UPS pod rests on a structural steel support beam anchored to a concrete pier. The pier top elevation is set at minus one foot nine inches with sizing and reinforcing per plan. A one-half inch galvanized shim plate sits directly on the concrete pier underneath the steel beam flange, leveled with a one and one-half inch grout pack. Anchor bolts embedded within the concrete pier secure the base assembly.
FINISH GRADE ELEV. VARIES. CONCRETE PIER. SEE PLAN FOR SIZE AND REINF. T.O. PIER EL. = -1'-9" 1 1/2" GROUT 1/2" GALV. SHIM PLATE 3A S3-01 1'-6" 1/2" 3/4" 1 1/2" UPS POD UPS POD SUPPORT BEAM, BY POD MANUF.