Option 1 connects the concrete slab-on-grade to the concrete tilt-up panel using number 4 by two foot six inch dowels spaced at eighteen inches on center with one threaded end tied into a Lenton Form Saver and a one half inch diameter HSA anchor. Option 2 ties the slab directly to the panel using number 4 by two foot six inch dowels epoxied into the concrete tilt-up panel at eighteen inches on center. Both options maintain a minimum one and a half inch concrete cover.
1 1/2" COVER (MIN.) OPTION #2 OPTION #1 CONC SLAB ON GRADE CONC SLAB ON GRADE #4 x 2'-6" DOWEL @ 18" O.C. THREADED ONE END LENTON FORM SAVER CONC TILT-UP PANEL CONC TILT-UP PANEL. 1/2" DIA. HSA. #4 x 2'-6" DOWEL @ 18" O.C. EPOXIED INTO CONC TILT-UP PANEL 1 1/2" COVER (MIN.)