A concrete pour construction joint is positioned parallel to the metal deck span over supporting steel framing. The joint location requires a minimum offset of two feet from the beam centerline or one-eighth of the beam span length, whichever is greater, separating the first and second concrete pours.
CL BEAM 1ST POUR 2ND POUR 2'-0" MIN CONSTRUCTION JOINT LOCATION BEAM L=BEAM SPAN L/8 MINIMUM B CONSTRUCTION JOINT PARALLEL TO DECK SPAN CL BEAM 1ST POUR 2ND POUR 2'-0" MIN CONSTRUCTION JOINT LOCATION BEAM L=BEAM SPAN L/8 MINIMUM B CONSTRUCTION JOINT PARALLEL TO DECK SPAN