Collector reinforcement utilizes Lenton C2 weldable couplers anchored within a concrete element and frames into a steel beam per plan. The assembly features specific tie layouts above and below the collector bars with defined spacing intervals of two and four inches. Reinforcement sizing and placement follow structural elevations and framing plans.
GRID 1'-3" 4" 2" 2" 4" COLLECTOR REINF. PER ELEVATIONS W/ LENTON C2 WELDABLE COUPLERS REINF. PER ELEV. & A B COLLECTOR REINF. PER ELEV. 4" 4" 2" 2" 2" STL BM PER PLAN COLLECTOR REINF. PER PLAN TEXT COLLECTOR REINF. PER ELEVATIONS W/ LENTON C2 WELDABLE COUPLERS TIE LAYOUT ABOVE & BELOW COLLECTOR BARS SHOWN