A horizontal construction pour joint within a concrete wall assembly features a roughened and cleaned surface to ensure bond between concrete placements. Vertical reinforcement continuous through the joint is accompanied by horizontal reinforcement occurring as specified. A minimum three-eighths inch clearance is maintained at horizontal reinforcement, and a one-and-one-half-inch offset or dimension marks the joint transition. Cleanouts are provided at the vertical reinforcement whenever the concrete pour height exceeds five feet.
1 1/2" CONSTRUCTION/ POUR JOINT PROVIDE CLEANOUT AT VERTICAL REINF WHERE POUR HEIGHT EXCEEDS FIVE FEET ROUGHEN AND CLEAN 3/8" CLEAR MIN AT HORIZ REINF HORIZ REINF WHERE OCCURS VERTICAL REINF