This trench section details a utility duct bank installation in a non-traffic area with a minimum 36-inch cover and a 48-inch maximum depth. The conduit rests upon a 4-inch sand bedding layer inside the trench excavation, with sand backfill free of rocks over 10 inches in diameter surrounding the bank. A warning tape is placed 12 inches above the duct bank beneath the roadside final grade. Sand shading of 6 or 12 inches is applied after compaction.
32" (TYP) 24" MIN 48" MAX 2 1 1. WARNING TAPE. PLACE 12" ABOVE DUCT BANK. 2. SAND BACKFILL (NO ROCKS OVER 10" DIAMETER). 3. 6" OR 12" SAND SHADING AFTER COMPACTION. 4. ROADSIDE FINAL GRADE. 5. EXCAVATED DIRT PILE. 6. 36" MIN COVER. 7. 4" SAND BEDDING. 8. REFER TO CONDUIT BANK SECTIONS. NOTES: 3 9" 9" D 4 5 6 7 8 NON-TRAFFIC AREA NONE 1 TYPICAL DUCT-BANK SECTION (TRAFFIC AND NON-TRAFFIC AREA)